Modeling Time and Cost Using LPS and VSM Techniques for Linear Project Success

Document Type : Original Article

Authors
1 PhD student. Department of Civil Engineering, Sanandaj Branch, Islamic Azad University, Sanandaj, Iran
2 Assistant professor. Department of Industrial Engineering, Sanandaj Branch, Islamic Azad University, Sanandaj, Iran
3 Assistant professor. Department of Civil Engineering, Sanandaj Branch, Islamic Azad University, Sanandaj, Iran
4 Associate Professor. Department of Statistics, Sanandaj Branch, Islamic Azad University, Sanandaj, Iran
Abstract
Lean construction is one of the most effective modern approaches for reducing project time and costs. In the construction industry, linear projects face challenges due to significant waste and repetitive operational processes, with numerous factors influencing their success. Given that previous studies have rarely examined precise modeling of success factors and their relationship to the performance of linear projects, the primary aim of this research is to model and analyze time and cost factors in linear projects using lean construction techniques—specifically, the Last Planner System (LPS) and Value Stream Mapping (VSM)—to reduce time and cost waste, thereby enhancing performance, reducing risks, and increasing productivity in the lean construction industry. This study, centered on modeling success factors in linear projects, seeks to minimize and eliminate waste. Structural Equation Modeling (SEM) was employed to analyze data and examine the relationship between techniques and project success. The findings demonstrate that implementing the Last Planner System and Value Stream Mapping significantly reduces time and cost waste, ultimately improving project success. These techniques enhance project productivity by optimizing workflows, improving resource management, and reducing unnecessary activities, helping to achieve goals such as timely project completion, cost control, and improved execution quality. Additionally, results indicate that the Last Planner System has a greater impact on reducing time waste, whereas Value Stream Mapping is more effective in reducing cost waste. Finally, this research recommends that clients and project managers of linear projects utilize lean construction techniques to improve overall project performance and increase the likelihood of success.
Keywords

Subjects


[1] Al-Aomar, R. (2012). A lean construction framework with Six Sigma rating. International Journal of Lean Six Sigma, 3 (4): p. 299-314.
[2] Othman, M.I.S., et al. (2023). Project Management Practices to Empower Lean Construction in Malaysia's Construction Industry. Research in Management of Technology and Business. 4 (1): p. 961-978.
[3] Noorzai, E. (2023). Evaluating lean techniques to improve success factors in the construction phase. Construction Innovation. 23 (3): p. 622-639.
[4] Womack, J.P., D.T. Jones, and D. Roos. (2007). the machine that changed the world: The story of lean production--Toyota's secret weapon in the global car wars that is now revolutionizing world industry. Simon and Schuster.
[5] Ghosh, S. and J. Burghart. (2021). Lean Construction: Experience of US Contractors. International Journal of Construction Education and Research. 17(2): p.153-133.
[6] Al Balkhy, W., R. Sweis, and Z. Lafhaj. (2021). Barriers to Adopting Lean Construction in the Construction Industry—The Case of Jordan. Buildings. 11 (6): p.222.
[7] Al-Tmeemy SH, Abdul-Rahman H, Harun Z (2010) Future Criteria for Success of Building Projects in Malaysia. International Journal of Project Management 29: 348-337.  
[8] Lim, C. and M.Z. Mohamed. (1999). Criteria of project success: an exploratory re-examination. International journal of project management. 17 (4): p. 243-248.
[9] Damoah, I., A. Ayakwah, and P. Twum. (2022). Assessing public sector road construction projects’ critical success factors in a developing economy: Definitive stakeholders’ perspective. Journal of Project Management. 7 (1): p. 23. 23-34.
[10] Mwelu, N., et al. (2021). Success factors for implementing Uganda’s public road construction projects. International Journal of Construction Management. 21 (6): p.614-598.  
[11] Aziz, R.F. and S.M. Hafez (2013). applying lean thinking in construction and performance improvement. Alexandria Engineering Journal. 52 (4): p. 679-695.
[12] Koskela, L. and G. Howell. (2002). The theory of project management: Explanation to novel methods. in Proceedings IGLC.
[13] Fang, Y. and Daniel, E.I. (2021). Defining Lean Construction Capability from an Ambidextrous Perspective. Proceedings of the 29th Annual Conference of the International Group for Lean Construction (IGLC29), Alarcon, L.F. and González, V.A. (eds.) , Lima, Peru, pp. 147–156, doi.org/10.24928/2021/0105.
[14] Singh, S. and K. Kumar. (2020). Review of literature of lean construction and lean tools using systematic literature review technique (2008–2018). Ain Shams Engineering Journal. 11 (2): p. 465-471.
[15] Ahmed, S., M.M. Hossain, and I. Haq. (2021). Implementation of lean construction in the construction industry in Bangladesh: awareness, benefits and challenges. International Journal of Building Pathology and Adaptation. 39 (2): p. 368-406.
[16] Mossman, A. (2018). What is lean construction: another look-2018. in 26th Annual Conference of the International Group for Lean Construction.
[17] Ango, A. and I. Saidu. (2021). ASSESSMENT OF LEAN TECHNIQUES FOR BUILDING MATERIALS WASTE MINIMISATION IN ABUJA, NIGERIA. P: 368-406.
[18] Shaqour, E. (2021). The impact of adopting lean construction in Egypt: Level of knowledge, application, and benefits. Ain Shams Engineering Journal.
[19] Aslam, M., Z. Gao, and G. Smith. (2021). Integrated implementation of Virtual Design and Construction (VDC) and lean project delivery system (LPDS). Journal of Building Engineering: p. 102252.
[20] M. Farag and F. (2008). Gehbauer, Egyptian Highway Construction Projects in Need of Lean Management, Al-Azhar University Engineering Journal, JAUES 2008 Vol. 3 Issue 10 Pages 483-491
[21] Liu, S.-S. and C.-J. Wang. (2007). Optimization model for resource assignment problems of linear construction projects. Automation in Construction. 16(4): p. 460-473.
[22] Kallantzis, A. and S. Lambropoulos. (2004). Discussion of “Comparison of linear scheduling model and repetitive scheduling method” by Kris G. Mattila and Amy Park. Journal of Construction Engineering and Management. 130 (3): p. 463-467.
[23] Sari, E.M., et al. (2021). Partnering Tools to Achieve Lean Construction Goals. PalArch's Journal of Archaeology of Egypt/Egyptology. 18(4): p. 6727-6739.
[24] Matt, D.T., P. Dallasega, and E. Rauch. (2015). On-site oriented capacity regulation for fabrication shops in Engineer-to-Order companies (ETO). Procedia CIRP. 33: p. 197-202.
[25] Womack, J.P. (1990). D.T. Jones, and D. Roos, the machine that changed the world, Rawson Associates. New York. 323: p. 273-287.
[26] Ansah, R.H., S. Sorooshian, and S.B. Mustafa. (2016). Lean construction: an effective approach for project management. ARPN Journal of Engineering and Applied Sciences. 11(3): p. 1607-1612.
[27] Chavan, V. I. N. O. D., Waghmare, A. P., Shelke, D. N., & Vispute, G. A. U. R. A. V. (2021). Work sampling and value stream mapping of lean construction. Iconic Res Eng J, 104-110.
[28] Ballard, G. (2008). The lean project delivery system: An update. Lean construction journal, 2008: p. 1-19.
 [29] Bajjou, M.S. and A. Chafi. (2020). Identifying and managing critical waste factors for lean construction projects. Engineering Management Journal. 32(1): p. 2-13.
[30] Yücenur, G.N. and K. Şenol. (2021). Sequential SWARA and fuzzy VIKOR methods in elimination of waste and creation of lean construction processes. Journal of Building Engineering. 44: p. 103196.
[31] Michalski, A., E. Głodziński, and K. (2022). Bӧde, Lean construction management techniques and BIM technology–systematic literature review. Procedia Computer Science. 196: p. 1036-1043.
[32] Fernandez-Solis, J.L., et al. (2013). Survey of motivations, benefits, and implementation challenges of last planner system users. Journal of construction engineering and management. 139 (4): p. 354-360.
[33] Salama, T., A. Salah, and O. Moselhi. (2021). Integrating critical chain project management with last planner system for linear scheduling of modular construction. Construction Innovation.
[34] Zahraee, S.M., et al. (2021). Lean construction analysis of concrete pouring process using value stream mapping and Arena based simulation model. Materials Today: Proceedings. 42: p. 1279-1286.
[35] Enshassi, A., N. Saleh, and S. Mohamed. (2021). Barriers to the application of lean construction techniques concerning safety improvement in construction projects. International Journal of Construction Management. 21 (10): p. 1044
[36] Ogunbiyi, O., J.S. Goulding, and A. Oladapo. (2014). An empirical study of the impact of lean construction techniques on sustainable construction in the UK. Construction innovation.
 [37] Glaser, B.G. and A.L. (1967). Strauss, the discovery of grounded theory: strategies for qualitative research (grounded theory). Taylor & Francis eBooks DRM Free Collection.
[38] De Vet, H.C., et al. (2017). Spearman–Brown prophecy formula and Cronbach's alpha: different faces of reliability and opportunities for new applications. Journal of Clinical Epidemiology. 85: p. 45-49.
Volume 12, Issue 08 - Serial Number 97
November 2025
Pages 166-187

  • Receive Date 16 September 2024
  • Revise Date 01 November 2024
  • Accept Date 30 December 2024