Evaluation of scheduling effects on construction project delays

Document Type : Original Article

Authors
1 PhD student, Department of Civil Engineering, Iran University of Science and Technology, Tehran, Iran
2 Associate Professor, Department of Civil Engineering, Iran University of Science and Technology, Tehran, Iran.
Abstract
Delays are one of the most important problems in the construction industry, because delays in construction projects have negative effects on owners and contractors. The aim of this study is to evaluate the effects of scheduling on construction project delays. The methodology of this research was to use a questionnaire and analyze the results quantitatively. In this regard, fifteen companies were selected from the three groups of employer, consultant and contractor, and the prepared questionnaire was sent to 80 of their employees. Finally, 70 participants answered the questionnaires, and the obtained data were analyzed using SPSS statistical software. The results of the analysis show that the most important objectives of scheduling in construction projects are "resolving conflicts between suppliers or sub-contractors", "use as an effective project control tool" and "resolving delay claims". In addition, based on the evaluation, the importance of the initial schedule in construction, "timely completion of projects" and "ensuring customer satisfaction" were determined. Also, delays and disruptions in construction projects were recognized as the consequences of lack of scheduling in construction projects. Finally, it was concluded that to minimize delays and also to ensure timely delivery of the construction project, project objectives, importance and effects of scheduling are key factors that should be considered to avoid delays.
Keywords

Subjects


[1]        H. Danso and J. K. Antwi, "Evaluation of the factors influencing time and cost overruns in telecom tower construction in Ghana," Civil & Environmental Research, vol. 2, no. 6, pp. 15-24, 2012.
[2]        S. A. Assaf and S. Al-Hejji, "Causes of delay in large construction projects," International journal of project management, vol. 24, no. 4, pp. 349-357, 2006.
[3]        A. Akinsola, "Neural network model for predicting building projects’ contingency’," in Conference: proceedings of association of researchers in construction management, ARCOM, 1996, vol. 96, pp. 507-16.
[4]        S. Alkass, M. Mazerolle, and F. Harris, "Construction delay analysis techniques," Construction Management & Economics, vol. 14, no. 5, pp. 375-394, 1996.
[5]        S. T. Ng, M. Skitmore, M. Z. Deng, and A. Nadeem, "Improving existing delay analysis techniques for the establishment of delay liabilities," Construction Innovation, vol. 4, no. 1, pp. 3-17, 2004.
[6]        S. B. Mohan and K. S. Al-Gahtani, "Current delay analysis techniques and improvements," Cost Engineering, vol. 48, no. 9, p. 12, 2006.
[7]        J.-B. Yang and P.-C. Yin, "Isolated collapsed but-for delay analysis methodology," Journal of Construction Engineering & Management, vol. 135, no. 7, pp. 570-578, 2009.
[8]        S. A. Mubarak, Construction project scheduling and control. John Wiley & Sons, 2015.
[9]        T. J. Trauner, Construction delays: Understanding them clearly, analyzing them correctly. Butterworth-Heinemann, 2009.
[10]      Oxley, R. & Poskitt, J. (1996). Management Techniques Applied to the Construction Industry. Blackwell Science Publishing, Great Britain.
[11]      Oberlender, G. D. (2000). Project Management for Engineering and Construction. McGraw-Hill, Singapore.
[12]      Callahan, M. T., Quackenbush, D. G. & Rowings, J. E. (1992). Construction Project Scheduling. McGraw-Hill, USA.."
[13]      K. Pickavance, A. Burr, and A. Axelson, "Delay and disruption in construction contracts LLP," ed: Reference Publishing, London, 2005.
[14]      M. Sambasivan and Y. W. Soon, "Causes and effects of delays in Malaysian construction industry," International Journal of project management, vol. 25, no. 5, pp. 517-526, 2007.
[15]      N. Hamzah, M. A. Khoiry, I. Arshad, N. M. Tawil, and A. C. Ani, "Cause of construction delay-Theoretical framework," Procedia engineering, vol. 20, pp. 490-495, 2011.
[16]      Syed M., Ahmed, S. A., Mauricio, C. & Pragnya, K. (2002). Construction Delays in Florida: An Empirical Study.
[17]      M. R. Finke, "Window analyses of compensable delays," Journal of Construction Engineering & Management, vol. 125, no. 2, pp. 96-100, 1999.
[18]      M. R. Manavazhi and D. K. Adhikari, "Material and equipment procurement delays in highway projects in Nepal," International Journal of Project Management, vol. 20, no. 8, pp. 627-632, 2002.
[19]      K. S. Wei, "Causes, effects and methods of minimizing delays in construction projects," A project report, 2010.
[20]      S. Howick, F. Ackermann, C. Eden, and T. Williams, "Understanding the causes and consequences of disruption and delay in complex projects: how system dynamics can help," 2009.
[21]      M. Abd El-Razek, H. Bassioni, and A. Mobarak, "Causes of delay in building construction projects in Egypt," Journal of construction engineering & management, vol. 134, no. 11, pp. 831-841, 2008.
[22]      S. A. Assaf, M. Al-Khalil, and M. Al-Hazmi, "Causes of delay in large building construction projects," Journal of management in engineering, vol. 11, no. 2, pp. 45-50, 1995.
[23]      A. M. Odeh and H. T. Battaineh, "Causes of construction delay: traditional contracts," International journal of project management, vol. 20, no. 1, pp. 67-73, 2002.
[24]      M. I. Wahdan, A. Farid, and M. Abu Yousef, "Study and Assessment of the Reasons for Project Delay or Stalled from Project Management View," Jeaconf. org, 2013.
[25]      L. A. D. Looff and L. D. Loff, Information systems outsourcing decision making: a managerial approach. IGI Global, 1996.

  • Receive Date 12 October 2023
  • Revise Date 26 July 2024
  • Accept Date 25 December 2023