Evaluation of delay criteria in water and sewage infrastructure projects in Bushehr province

Document Type : Original Article

Authors

1 Management of development projects

2 Department of Civil Engineering, Estahban Branch, Islamic Azad University, Estahban, Iran

Abstract

The main goal of this research was to assess the criteria pertaining to delays in infrastructure projects of Bushehr Water and Sewerage Company. Assessments were conducted by library studies, interviews, and questionnaires. The relating factors were provided to the statistical population in the form of a questionnaire. Subsequently, using the fuzzy TOPSIS method, the most effective factors were calculated and then the factors were introduced by degree of effectiveness. The statistical population of this research was divided into three categories with different responsibilities, characteristics, and perspectives as follows: Consulting engineers, Contracting companies, and Employer. Purposeful and available sampling method was used to determine the sample size and 30 persons were considered as the statistical sample. In this study, the factors influencing water and sewage project delays were identified in four categories of factors caused by financial issues, resources and materials, manpower management, and the knowledge and experience of the contractor, as well as 28 sub-criteria. Ranking factors effective in Bushehr water and sewage project delays indicated that the most important ones of these factors by importance respectively are: Failure to pay the contractor's claims on time; Inefficient manpower management and poor quality of work performed by the contractor; Lack of pricing by contractors to win the tender; Weak history or low number of contractor's technical and executive personnel; and Poor work planning due to inexperienced contractor.

Keywords

Main Subjects


[1] Davari, Kamran, (2006), A Study of the Use of Project Management in Water and Sewerage Projects A Case Study of Sewerage Project Management in Neishabour, Torbat Heydariyeh and Sabzevar Ansari Hossein, The First National Conference on Irrigation and Drainage Networks Management, Ahvaz, Chamran University.
[2] Aziz, R. F. (2013). Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, 52(3), 387-406.
[3] M.F. Nagata, W.A. Manginelli, J.S. Lowe, T.J. Trauner,(2018), Chapter Eighteen - Delays and the Contract, in: Construction Delays (Third Edition), Butterworth-Heinemann, 2018, pp. 355-385.
[4] Sambasivan, M., & Soon, Y.W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25: 517–526.
[5] Mosalman Yazdi, H., Mosalman Yazdi, M., Mohammadi, E. (2019). Delay Determination of Subway Construction Project by Fuzzy MCDM (Case Study, Karaj Subway). Amirkabir Journal of Civil Engineering, 51(1), 143-156.
[6] Hazri, Farshad, (2014), Investigating the causes of delays in construction projects in Mashhad and presenting solutions to get out of it, Master Thesis, Ferdowsi University of Mashhad.
[7] Heydariyeh, Seyed Abdullah, Kheirandish Ali, Ali, (2016), Identifying and prioritizing the causes of delays in wastewater collection network development projects by FAHP fuzzy hierarchy analysis, Conference on Applied Research in Industrial Management, Semnan, Islamic Azad University, Semnan Branch.
[8] Mo'meni, Abolfazl; Khairkhah, Amirsaman. (2007). Multi-project budgeting model to prevent project delays, International Project Management Conference
[9] Aziz, R. F., & Abdel-Hakam, A. A. (2016). Exploring delay causes of road const ruct ion projects in Egypt. Alexandria Engineering Journal, 55(2), 1515-1539.
[10] Assaf, A. and Al-Heji, S. (2006) “Causes of delay in large construction projects.” International Journal of Project Management 24, pp. 349–357
[11] Le-Hoai, L., Dai Lee, Y. and Yong Lee, J. (2008) "Delay and Cost Overruns in Vietnam Large Construction Projects: A Comparison with Other Selected Countries". KSCE Journal of Civil Engineering 12, pp. 367-377
[12] Fugar, F. D. and Agyakwah-Baah, A. B. (2010). "Delays in building construction projects in Ghana." Australasian Journal of Construction Economics and Building, 10, pp. 103-116.
[13] Haseeb, M., Lu, X., Bibi, A., Dyian, M. and Rabbani, W. (2011). " Causes and Effects of Delays in Large Construction Projects of Pakistan". Australian Journal of Business and Management, 5, pp. 41-50.
[14] Hamzaha, N., Khoirya, M.A., Arshada, I., Tawilb, N.M. and Che Ani, A.I. (2011) “Cause of construction delay theoretical framework”. Procedia Engineering 20, pp. 490 – 495
[15] Doloi, H., Sawhney, A., Iyer, K. C. and Rentala, S. (2012). "Analysing factors affecting delays in Indian construction projects". International Journal of Project Management, 30, pp. 479– 489.
[16] Pourrostami, T., (2011), "Significant effective factors and effects of delays in Iran's infrastructure projects".
[17] Fateh, Mohammad Ali, Valipour, Ali Reza, (2017), Investigating the causes of delays in construction projects with emphasis on problems in human resource management, 2nd International Conference on Civil Engineering, Architecture and Crisis Management, Tehran, Allameh Majlisi University.